1. The pile driver is composed of a crawler crane and a diesel pile hammer or a vibrating pile hammer. When operating, the respective safety and technical instructions must be strictly followed. Among them, the crawler crane needs to check whether the hydraulic system, lifting mechanism, etc. are normal according to its operating procedures; Dieselhöghammaren måste uppmärksamma bränsletillförseln och smörjningen av hammarkroppen, och den vibrerande höghammeren måste bekräfta mängden smörjolja i vibrationslådan och motorens driftsstatus för att säkerställa att de olika komponenterna fungerar tillsammans och i överensstämmelse .}
2. The installation site of the pile driver must be flat and solid. If the bearing capacity of the foundation is insufficient, a roadbed box or a 30mm thick steel plate must be laid under the crawler, and the laying spacing must not exceed 300mm. When laying, it is necessary to ensure that the steel plate or roadbed box is flat and warped, and in close contact with the ground För att sprida trycket under driften av högföraren, förhindra att utrustningen lutar på grund av grundläggande avveckling och ge stabilt grundstöd för högkörningsoperationen .
3. The installation and disassembly of the pile driver must be strictly carried out according to the procedures specified in the factory manual. For pile drivers with telescopic crawlers, the crawlers should be expanded before installation. This operation needs to be performed without counterweight, and the upper slewing platform should be turned to a 90℃position with the crawlers to ensure the Balansen mellan flygkroppen under expansionsprocessen . Under expansionen är det nödvändigt att observera om den crawler teleskopiska mekanismen går smidigt . efter att ha bekräftat att det inte finns någon fastställning, fortsätt med de efterföljande installationsstegen för att undvika utrustning på grund av felaktig drift .}}}}
4. Once the column base is in place, the horizontal fine-tuning hydraulic cylinder should be tested. During the trial, the hydraulic system should be gradually operated with the purpose of inspecting whether the hydraulic cylinder is stable and whether there are oil leakages.After verification of its good condition, the piston rod is pulled out in preparation for the installation of the column.After the verification of it operating normally, the piston rod is pulled out to prepare for column installation.During the trial, working pressure and stroke information of the hydraulic cylinder should be measured in order to ensure that its performance is up to the requirements of installation in case the failure of the base adjustment mechanism after column installation affects the overall Stabilitet .
5. When installing the column, the crawler drive wheel should be placed at the rear, and the front tipping point of the crawler should be filled with iron wedges. At the same time, the brake stop mechanism and slewing mechanism should be braked to prevent the equipment from moving during installation. Following the placement of the horizontal telescopic arm with the pin, while placing the Vertikal hydraulisk cylinder, det bör finnas en träkudde placerad under den för att balansera huvudmaskinen . Kolonnens vertikalitet bör övervakas samtidigt under installationen, och förlängningslängden för den vertikala hydrauliska cylindern ska justeras så att kolonnen är exakt vinklad till marken för förhindrande av högutrustning)